From STEP file to your door: a realistic CNC prototype timeline

How long does a CNC prototype take from China? The honest answer is a set of stages, each with a typical range. This guide walks through them in order, adds them up, and shows what moves the date.

Every range below is typical, not a promise. Your actual lead time is confirmed on your quote.

The stages, in order

StageTypical time
1. Quote, from receiving your filesWithin 48 hours
2. Order confirmation and depositLead time typically starts when the deposit is received
3. Free DFM review1–3 days
4. Machining a prototype10–15 business days
5. Air freight (FedEx or DHL)7–12 days

1. Quote within 48 hours

There is no online store: you send files and receive a quote, within 48 hours of us receiving them. Quotes are valid for 30 days, and every drawing gets a dedicated project contact.

2. Order confirmation locks the lead time

When you confirm the order, the schedule is set. Lead time typically starts when the deposit is received, so the quote days come before it. If you want samples approved first, that is an optional step at this point.

3. Free DFM review, 1–3 days

After you confirm the order, every drawing gets one free, full DFM (design for manufacturability) review. It takes 1–3 days and happens before machining begins. We keep confirming specs with you while your parts are made: interim DFM reviews during machining, plus quick confirmations whenever a question comes up. See CNC DFM basics.

4. Machining: typically 10–15 business days

Prototypes typically take 10–15 business days; production orders typically take 15–30. Quantity moves the lead time less than people expect: 200 parts is around 15 days, and 1,000 often adds only a few days.

5-axis CNC milling on the Fenva Precision production floor

5-axis milling on our production floor.

5. Shipping: about 7–12 days by air

Prototypes usually fly. Air shipments go through FedEx or DHL and leave via Shanghai Pudong International Airport; we arrange export clearance ourselves. Typical transit is 7–12 days by air. For larger production orders, rail (25–35 days) and sea (39–65 days, via the Port of Ningbo) are slower and lower-cost options. Transit times vary by destination and customs. See shipping and Incoterms.

A worked example

Adding the typical ranges: quote within 2 days, DFM review in 1–3 days, 10–15 business days of machining (2–3 calendar weeks), then 7–12 days by air. From first files to delivery, that is roughly 3½ to 5½ weeks. It is an estimate built from typical ranges, not a delivery date; your quote confirms the actual lead time.

What moves the date

  • Material. Common grades (6061, 7075, 304, common carbon and alloy steels) are usually ready to cut in a couple of days. Specialty alloys are sourced to order and can add a week or more. This is the main variable.
  • Finish. Finishing runs as a batch, and some finishes (chrome and nickel plating, powder coat, black oxide) are run by specialist partners we coordinate. Specify the finish when you ask for the quote.
  • Quantity. Less than you might think: see the examples above.

How to brief us for speed

  • Send a 3D STEP file plus a 2D PDF with tolerances, quantity, material and finish. With 3D only, parts are machined to ISO 2768-m general tolerance; with 2D only, the price is an estimate until we receive the model.
  • Accepted files: STEP, IGES, X_T, X_B, SLDPRT, IPT, DWG, DXF, STL, PDF, ZIP/RAR/7Z.
  • An NDA is available on request, and we are happy to sign first.

For a checklist, see how to get an accurate CNC quote. We machine from one prototype to production, with no minimum order.

Request a quote Ordering process
Export crate with foam-packed CNC parts ready for shipment

Prototypes

Send the STEP and PDF. Get a quote in 48 hours.

Prototypes typically 10–15 business days, production typically 15–30, confirmed on your quote. No minimum order.